8

I

NSTALLATION

Preparation

1. Visually inspect the UPS for freight damage. Report damage to the carrier

and your local dealer or Liebert representative.

2. Decide where to place the Liebert GXT2U. Install the UPS indoors in a con-

trolled environment, where it cannot be accidentally turned off. Place it in

an area of unrestricted airflow around the unit, away from water, flamma-

ble liquids, gases, corrosives, and conductive contaminants. Maintain a

minimum clearance of 4 inches (100mm) in the front and rear of the UPS.

Maintain an ambient temperature range of 32°F to 104°F (0°C to 40°C).

3. The Liebert GXT2U may be installed in either a tower configuration or in a

rack, depending on available space and use considerations. Determine the

type of installation and follow the appropriate instructions in either Tower

UPS Installation or Rack-Mount UPS Conversion and Installation.

Tower UPS Installation

When using the Liebert GXT2U in a tower configuration, use the included

support base (shown below, left) to stabilize the UPS.
If any battery cabinets are added, they will include spacers to accommodate

the additional cabinets (shown below, right).

!

CAUTION

The UPS is heavy (see Specifications section). Take proper

precautions when lifting or moving it.

NOTE
UPS operation in temperatures above 77°F (25°C) reduces battery

life.

Support base

Spacers added to support

base to accommodate

additional battery cabinets