4.4.2 Transport Using a Crane
1. Unscrew the base panels on the front and back; see 4.4.1 ”Transport Using a Pallet Truck or
2. Insert the fork of a crane under the cabinet.
NOTICE!
Inappropriate transport could cause damage to the Sunny Central.
In case of transport using a crane, the following points have to be observed:
• Asymmetric weight distribution
• Heavy duty
• The weight of the switch cabinet units is mainly distributed to the rear of the cabinet.
Transport using crane eyelets.
The heavy weight of the individual switch cabinet units means that transport using crane
eyelets is not permitted. A suitable crane fork should be used instead.