4.4 Transport Options
The inverter consists of two switch cabinet units, the DC / inverter cabinet and the AC cabinet, which
are separately transported and assembled together on site.
The inverters and switch cabinet units are delivered on pallets. A fork lift or a hoist is used to transport
the device to its final mounting location.
WARNING!
Heavy weight of the switch cabinet units!
Danger of tipping during transport!
• The cabinet units must always be transported in an upright position.
• When unloading, the heavy-load
markings must be given due
consideration.
– The center of gravity of the
Sunny Central is marked on the
outside of the packaging and on the
switch cabinet units.
– The labeling on the switch cabinet
units can be removed residue-free
following installation.
NOTICE!
Missing base panels could damage the Sunny Central.
• The base panels are essential for stable positioning of the switch cabinet.
• In the case of transport on a pallet, it is necessary to install the base panels.
Otherwise there is the danger that the base will collapse under the weight of the
switch cabinet.
Remove side base panels for cable routing
In the final installation location, one of the side base panels can be removed for cable
routing. The stability of the switch cabinet is still guaranteed.