Installation Requirements

SMA Solar Technology AG

18

SC-100-IEN093231

Installation Guide

Figure 5.2: Installation of the SC100 Outdoor with concrete foundation slab

The inverter cabinet must be installed on a level surface. Any existing unevenness, depressions or
slope must be corrected prior to installation.
When pouring the foundation, keep in mind that the cables and conduits should enter the inverter from
underneath. This means that suitable conduits or cable feed-throughs should be installed prior to
pouring.

Pouring and structural inspection of the foundation slab should be performed on-site.

NOTICE!

The cable must be routed into the inverter from below.

The cable routing through the removable base plates in the Sunny Central is displayed in
figure 5.3.

The control voltage and communication cables must be installed separately.

Sunny Central 100

SMA

Concrete foundation slab

Concrete foundation slab