6 commissioning the product, Commissioning the product – SMA AUTOMATIC SWITCH BOX L User Manual
Page 40
Commissioning the Product
SMA Solar Technology AG
40
AS-BoxL-IEN084410
Installation Guide
6 Commissioning the Product
1. Check the following requirements before commissioning:
– Automatic Switch Box is mounted securely to the wall.
– All cables are correctly and completely connected.
– All cables are tightly enclosed by the cable openings.
– The Automatic Switch Box has no voltage present.
2. Loosen screw caps of all fuse elements.
3. Insert headed sleeves into the fuse element "F6 generator".
4. Insert fuses into the screw caps.
5. Install screw caps, including fuse, into the fuse elements.
6. Switch on the circuit breaker in the Automatic Switch Box.
7. Lock Automatic Switch Box with the switch cabinet key.
8. Attach the included sticker (hazard warning for consumer load system) to a readily visible place
in or on the distribution that the Sunny Backup system is connected to. The hazard warning calls
attention to the Sunny Backup system and is intended to ensure that the Sunny Backup system
is also stopped during work that requires disconnection.
☑ The Automatic Switch Box is ready for operation.