beautypg.com

4 connecting the feed-in meter, Connecting the feed-in meter – SMA AUTOMATIC SWITCH BOX L User Manual

Page 23

background image

SMA Solar Technology AG

Electrical Connection

Installation Guide

AS-BoxL-IEN084410

23

5.4 Connecting the Feed-in Meter

Cable protection
For purposes of fuse protection and isolation, a line circuit breaker must be installed
between the Automatic Switch Box and the feed-in meter. Be sure to observe all standards
applicable to the installation site.

Connection requirements
The Sunny Backup system is only certified for TN grids and may not be installed in TT grids.
Comply with all connection regulations of your utility operator.

PV systems without a feed-in meter
The Sunny Backup system can also be used in PV systems without a feed-in meter. If you
do not connect a feed-in meter to the Automatic Switch Box, you must bridge the feed-in
meter (X5/PV Meter) and the consumption meter (X1/Load Meter) outside of the
Automatic Switch Box.