5  Mounting

SMA Solar Technology AG

12

METERBOXSBU-IA-en-40

Installation Manual

5 Mounting

5.1 Selecting the Mounting Location

Requirements for the mounting location:

☐ Mounting takes place indoor.
☐ The mounting location is protected against dust, moisture and corrosive substances.
☐ The mounting location is in the vicinity of a socket-outlet or an alternative voltage source.

Requirements for the cable routes:

☐ The cable route between the mounting location of the Meter Box, the mounting locations of the

Sunny Backup and the Automatic Switch Box is at maximum 20 m.

☐ Every cable route leading from the Meter Box to an energy meter is at maximum 2 m in length.

Observe minimum clearances:

Figure 4: Minimum clearances to be observed