HARVEST CYCLE - HOT GAS BYPASS

When the timer switches the icemaker into the
harvest cycle, high pressure, high temperature
refrigerant gas discharged from the compressor
flows through the hot gas solenoid valve into each
evaporator plate. During this cycle, the refrigerant
bypasses the condenser. In the electrical circuit,
both the compressor and the water pump are
operating. Both the hot gas solenoid valve and the
water inlet solenoid valve are OPEN.

The finished ice cubes are released from the sides
of each evaporator plate by the warming effect of
the hot gas condensing in each evaporator plate
and the water cascading over the ice cubes. The
released ice cubes drop into the ice storage bin
below. At the end of the harvest cycle, the timer
cam will push the actuator arm to the microswitch
IN. If the ice level control is still CLOSED, a whole
new cycle will begin. If the ice level control is
OPEN, the icemaker will begin to shut OFF.

Pump Down Cycle:

When the ice level control is open at the end of the
harvest cycle, power is removed from the liquid
line valve coil, and the pump down cycle begins.
The compressor will continue to run until the pump
down control, sensing low side pressure, opens at
15 PSIG.

Fan

Motor

Discharge

Line

Discharge

Coil

Heat

Exchange

Filter

Hot Gas

Valve

(Open)

Suction

Line

Liquid

Line Valve

TXV

Pump

Water

Valve

(Open)

Drain

Filter/Dryer

Receiver

Head

Pressure

Control

Valve

Liquid

Line

King

Valve

Evaporators

REFRIGERATION SCHEMATIC

Compressor

Crankcase

Heater

CME650R