2.2. siting the Machine

When siting the machine, the following have to be considered:
Site the machine on a fixed dry base, which does not cause dust etc. into the suction air of

cooling.
– Make sure that the machine is placed away from the line of particle spray from grinding

tools.

– Ensure free circulation of the cooling air. Make sure that there is at least a 20 cm free dis-

tance both in front of and at the rear of the machine for the circulation of the cooling air.

– Protect the machine against heavy rain and in hot circumstances against direct sunshine.

2.3. start of installation

Mastertig AC/DC 2500 and -2500W: Check first that the

mains voltage change-over switch is in right position.
If it is necessary to change mains cable, do it before moun-

ting to the wheel barrow T 120. Otherwise you possibly

have to dismount the machine.
Before connecting the machine to the mains supply, one

of the three panels, the ACDC panel, the ACDC minilog

or the ACDC pulse panel, has to be installed. Installation

instructions 4283280 are in the package of the panel.