20. Connect another 2 standard rigging rods to the first 2 standard rigging rods. Ensure

that the locking pins are inserted fully.

21. Connect the last 2 standard rigging rods to the 2 rigging rod connectors on arm

extension number 2. Ensure that the locking pins are inserted fully.

22. Hand tighten the rods by turning the turnbuckles until the rods are taut, then secure

the turnbuckles with the locking nut as seen on page 9.
Attention:

The rigging system when taut as well as the crane arm, should run in a
straight line and should not bend or dip.

23. Connect the platform to the angle adjuster and secure with the removed safety pin

from the side of the angle adjuster. Ensure that the platform is level.
Tip:

The angle adjuster has an integrated leveller. By turning it, the vertical plate
on the angle adjuster can be set to a perfect right angle. Correct setting of
the angle adjuster enhances the crane’s balance.

24. Remove the support stand or rostrum supporting the counterweight bucket section.
25. Then unlock the tilt friction.

Before operation, all locking pins, locking screws etc should be inspected to ensure
that all assembly sections are securely fastened.

Read “Balancing the crane arm” on page 44.