Installation Preparation
!
This appliance must be installed in accordance with all local codes, if any; if not, follow ANSI
Z223.1 and the requirements listed in this manual. Failure to follow all of the requirements
may result in property damage, bodily injury, or even death.
!
When installed in a mobile home, this appliance must be installed in accordance with the
Manufactured Home Construction and Safety Standard, Title 24 CFR, Part 3280, or if not
applicable, the Standard for Manufactured Home Installations (ANSI A225.1--1984).
!
Notify your insurance company before hooking up this stove.
!
The requirements listed below are divided into sections. All requirements must be met
simultaneously. The order of installation is not rigid Ð the qualified installer should follow the
procedure best suited for the installation.
Items Required for Installation
¥
Avanti Stove Shell
(Black #99200320, Almond #99200321, Green #99200322)
¥
Avanti Pedestal (Part # 99200115)
¥
Simpson Duravent with Silicone (see page 13 for part #'s)
¥
Gas Hookup Equipment
Items Packed with the Avanti DV
¥
Avanti DV (with gold door)
¥
Log Set (2 Logs, 2 Twigs, Coals)
¥
On/Off Switch (wired to the stove)
¥
Owner's Manual
¥
Gas Inlet Pipe (3/8" dia.)
Items Packed with the Stove Shell
¥
Top, Left, Right, and Rear Stove Panels
¥
Control Cover
¥
Black Grill
¥
Eight 10-32 Hex Nuts with Attached Lock Washers
¥
Two 10-24 Pan Head Screws
¥
Fourteen 10-24 Self-Tapping Screws
¥
Nine U-Nuts
¥
Two 6" strips of self-adhesive gasket
¥
Gas Line Plate
¥
Left & Right Forward Mounting Brackets
Items Packed with the Pedestal
¥
Pedestal
¥
Two 3/8 x 3/4" Bolts
¥
Two Washers
¥
Two Lag Bolts (these may be discarded)
Order of Installation
1
Remove the door and place aside
2
Attach the pedestal
3
Attach the stove panels to the stove
4
Install the gas inlet (included with the stove)
5
Position the stove , use floor protection if needed
6
Connect the gas line
7
Connect the gas vent
8
Remove the glass
9
Purge the gas line & leak test all gas line joints
10
Install the Logs
11
Replace the glass
12
Inspect the pilot, flames, and stove operation
Door Removal
(place aside during installation)
The door hangs on a pair of hooks on both
sides. Lift the door up and off the hooks to
remove. To replace, align the brackets on the
door over the hooks and slide downwards until
the door locks in place.
Hooks on Side
of Heater
Door
Bracket (on back
side of door)