Must, Mounting to solid concrete walls – One Systems Natatorium User Manual
Page 6
6
Mounting to Solid Concrete Walls:
(Concrete anchors are NOT ALLOWED for use with cinder block
construction)
IMPORTANT: IT IS THE RESPONSIBILITY OF THE INSTALLER TO
VERIFY THAT THE WALL SURFACE IS STRUCTURALLY CAPABLE
OF SUPPORTING THE PRODUCT AND ALL ASSOCIATED SAFETY
FACTORS AS REQURED BY ALL APPLICABLE CODES AND SAFE
SUSPENSION PRACTICES. THE INSTALLER SHOULD CONSULT
WITH A STRUCTURAL ENGINEER PRIOR TO INSTALLATION TO
INSURE THAT THE WALL SURFACE CAN SUPPORT THE WEIGHT
OF THE 112/NAT OR 108/NAT AND ALL ASSOCIATED RIGGING
AND ALL REQUIRED SAFETY FACTORS. THE COMPOSITION OF
THE WALL STRUCTURE
MUST
BE REVIEWED BY A
STRUCTURAL ENGINEER PRIOR TO INSTALLATION!
STOP: The approved anchors (Fischer FAZ II 10/10 C) require
a minimum solid concrete wall thickness of 3.937 inches
(100mm). DO NOT mount the NAT loudspeaker to a solid
concrete wall if the wall thickness is not at least 3.937 inches
(100mm) thick!
The NAT products are approved for use with the FAZ II 10/10C
for WALL mounting only! DO NOT MOUNT FROM A CEILING!
STOP: USING FAZ II 10/10 C ANCHORS REQUIRES A
TORQUE WRENCH CAPABLE OF 33 FT-LBS (45MN) OF
TORQUE. THESE ANCHORS MUST BE TORQUED TO THIS
VALUE. DO NOT INSTALL IF YOU DO NOT HAVE A
TORQUE WRENCH!
NOTE: The anchors referenced below are for use in solid concrete ONLY!
DO NOT use with cinder block (CMU) wall construction!
NOTE: ALL installation instructions below are guidelines. It is necessary to read the
additional installation instructions provided by Fischer. Additional instructions may
be found on the One Systems web site in the Documentation section. The Natatorium
section is found in the Tech Papers/Install guides section under the onesystems.com
Documentation Tab. This document is ESR 2948.