NSW INSTALLATION MANUAL

Electrical Data cont.

208 Volt Operation

All 208-230 volt units are factory wired for 230 volt

operation. To convert the unit from a 230V unit to a 208V

unit follow these steps:

1. Remove the blue transformer wire from terminal L2 on

the compressor contactor and secure the wire taking

care to insulate the end with electrical tape.

2. Locate the red transformer wire and connect it to the L2

terminal of the compressor contactor.

Electrical

Be sure the available power is the same voltage and phase

as that shown on the unit serial plate. Line and low voltage

wiring must be done in accordance with local codes or the

National Electric Code, whichever is applicable. Refer to

the Electrical Data table for wire and fuse or circuit breaker

sizing information.

Flow Center Pump Connection (208-230/60/1)

Two fuse internal terminal block connections with 1/4-inch

spade connectors are provided; one for the load pump

and one for the source pump. The source pump directly

connects to the fuse terminal block for the source pump.

The load pump directly connects to the fuse terminal block

for the load pump.

NSW Control Box Relocation

The NSW control box can be installed on the rear of the unit.

To relocate the control box, follow the procedures below.

1. Remove all power sources to the unit.

2. Remove the unit’s top panel.

3. Cut all plastic wire ties to the following:

a) High pressure switch (black wires)

b) Low pressure switch (blue wires)

c) Freeze sensing (yellow wires)

d) Load temperature sensor (black wires)

e)

Compressor

wires

4. Remove the four screws from the control box.

5. Relocate the control box to opposite end of the unit.

6. Using the screws removed in step 4 above, reattach the

control box.

7. Secure all wires so they do not come in contact with

refrigerant lines.

8. Replace the top of the unit.

9. Replace both access panels.

10. Reapply power sources.

NOTE: If geothermal storage tank is used, connect yellow

thermistor wires from the bottom access panel of the tank

to spade connectors 3 and 4 on the terminal block.