4 operation space, 5 front and back access, 6 final positioning – OPTI-UPS MD120L User Manual
Page 13: 7 power module installation
Chapter 1 Installation
10
开关单元
旁路模块
功率模块
配电单元
1.6m cabinet (front view) 1.6m cabinet (back view)
Fig 1-7 UPS Composition Diagram
Table 1-1 UPS Configuration Table
Involved part name
Quantity (Piece)
Note
Cabinet
Switch PDU
1
Standard configuration
Monitoring + bypass
module
1
Standard configuration
Power module
Power module
1~6 or 1~10
Field installation is
required
1.4.4 Operation Space
As UPS has no ventilation grills at either sides, no clearances are required for the sides.
To enable routine tightening of power terminations within the cabinet, it is recommended that
clearance around the front and back of the equipment should be sufficient to enable free passage of
personnel with the doors fully opened.
1.4.5 Front and Back Access
The component layout of the UPS supports front and back access for servicing, diagnosing and
repairing the UPS, thus reducing the space requirement for side access.
1.4.6 Final Positioning
When the equipment has been finally positioned, ensure the adjustable feet are set so that the UPS
will remain stationary and stable.
1.4.7 Power Module Installation
The installation position of power module and output distribution module are shown in fig 1-8. the
installation principle of these modules is to installed from bottom to top to prevent inclination of the
cabinet due to high center of gravity .
As is shown in fig 1-8, the installation procedure of power module is as follows:
switch unit
Switch unit
Bypass module
Power module
Distribution unit