27
Diagram 10.16
12847
Diagram 10.17
13254
10 Standard Flue - Length, Preparation and Installation
10.10 Flue Fitting
IMPORTANT:
The flue seals are sensitive to mineral oil based lubricants.
Do
not grease the seals. If the seals do need to be lubricated
use only water.
During the installation of the flue system, ensure that debris
such as mortar, filings or swarf are cleared from the flue
system before completion.
Long lengths of flues must be secured to the walls or ceilings
they run against. Use at least one clip for every flue extension
that is used.
After cutting inner flue tubes ensure that you de-burr and
chamfer the male tube end to prevent damage.
Inspect the flue pipes before fitting and do not install damaged
or dented flue components.
When assembling the flue system, ensure that the inner
seals are not damaged, do not install a flue component with a
damaged seal.
When fitting flue elbows ensure that they are fitted at the
correct angle to avoid strain, this will ensure that the seal fits
correctly preventing leakage.
Remove the flue elbow.
Separate the flue duct from the terminal by twisting to release
the terminal catch, then pull out of the retaining seal, refer to
diagram 10.16.
The flue duct cutting length (L + 11mm.) is shown in diagram
10.16.
The air duct should be cut at the opposite end to the terminal
The plastic flue duct MUST be cut at the opposite end to the
terminal catch.
The plastic flue duct extensions MUST be cut at the opposite
end to seal.
Insert the flue duct into the air duct terminal assembly,
remembering to engage the catch within the terminal.
Fit the sealing collar behind the locating lugs on the flue
terminal, see diagram 10.17.
Push the flue assembly into the wall, externally or internally,
initially until the end of the assembly protrudes a short way
from the inside face of the wall. This will enable the internal
trim ring (if required) to be positioned and allow the flue
assembly to be drawn back into the flue elbow.
Secure the flue elbow in position on top of the boiler with four
torque headed screws supplied.
Draw the flue assembly from wall and engage the flue duct
into the elbow and butt fit between the air duct and flue elbow.
Fit the securing collar into position.
Ensuring correct alignment of the flue, mark through two of the
pre drilled holes in the securing collar.
Remove securing collar and drill two 3mm diameter holes one
in the elbow and one in the air duct, take care not to pierce the
inner flue duct. Fit the securing collar and secure with screws
provided, see diagram 10.17.
Slide the internal trim ring back against the wall, securing in
place with a small amount of sealant if required.
NOTE: If the air and flue ducts have been correctly cut to the
instructions the sealing collar should fit flush with the outside