14 Commissioning
Important: The commissioning and first firing of the boiler must
only be done by a competant person.
Gas installation
If conversion from G20 to 30 or 31 is required, refer to section
16.
It is recommended that any air is purged from the supply at the
gas purge point on the gas valve, see diagram 14.1.
Filling the system 1 to 8
11548
11547
GAS PURGE
POINT
Diagram 14.1
3.
• Undo cap on automatic air vent on top of
pump and leave undone.
1.
Make sure that:
• The boiler is connected to the electrical supply.
• The gas service cock is open.
Switch OFF ( 0 )
11927
2.
• Open the three water isolating valves.
HEATING
RETURN
COLD
WATER
INLET
HEATING
FLOW
DOMESTIC
HOT WATER
OUTLET
GAS
SERVICE
COCK
11445
Air in pipes
Important: A central heating system can not operate correctly
unless it is filled with water and air bled from the system. If these
conditions are not met the system may be noisy.
Bleed the air in the radiators and adjust the pressure if system
requires. If the system requires filling to often this may be due
to minor leaks or corrosion in the system.
Note: Isolating valves are shown in the: OFF position
• Turn the switch ON ( I )
• Open the tap on the filling device
• Fill the system until the pressure indicated on
the display is 1 bar. Close filling device.
9792
4.
➜
NOTE: On initial fill there may be a small discharge
of water from the Reduced Pressure Zone valve
➜
BURNER
PRESSURE
POINT