beautypg.com

Carrier 16JB User Manual

Page 2

Attention! The text in this document has been recognized automatically. To view the original document, you can use the "Original mode".

background image

Start-Up Demand

— Steam demand by the absorp­

tion machine is greatest at start-up (see Table 1 for
values).

Table 1 — Maximum Condensate Flow (Ib/hr)

VALVE

VALVE INLET STEAM PRESSURE

SIZE (in.)

20 psig

14 psig

12 psig

10 psig

2

2450

2025

1880

1750

2Y2

4825

4000

3710

3430

3

8175

6760

6285

5810

4

14540

12025

11190

10350

5

21650

17900

16655

15400

When boiler capacity is unable to keep up with

start-up demand, the steam pressure will fall off.
On boilers serving only the absorption machine,
this reduction in steam pressure will have no
adverse effect on the absorption machine other
than to lengthen start-up time. However, the
increased steam demand may have an adverse
effect on the boiler, causing it to run dry and fail.
As steam pressure is reduced, the steam control
valve pressure drop will eventually limit the de­
mand on the boiler provided the steam control
valve is properly sized.

On boilers serving other loads simultaneously,

the start-up demand can reduce boiler pressure

sufficiently to cause adverse effects on other
steam-driven equipment. When a reduction in

boiler pressure cannot be tolerated without up­

setting other equipment, the boiler capacity avail­
able for absorption machine operation (with other
loads deducted) must equal or exceed the start-up
demands. If it does not, the start-up demand can

be reduced by using demand Hmit controls, or
installing a back-pressure regulator in the steam
line(s) between the boiler and the control valve(s).
VALVE LOCATION AND PIPING - The steam

control valve should be located a minimum of 3 ft
away from the generator inlet. This is dictated by

good piping practice, to allow equal distribution of
steam in the generator tube bundle. Unequal
distribution of steam in the tube bundle may cause
a loss of capacity. Recommended steam supply
piping for low-pressure steam applications is
illustrated in Fig. 1.

STEAM CONTROt

NOTE; Separate supoiy piping "for each end of machine sizes

16JB077 thro '24,

Fig. 1 — Low-Pressure Steam (2 to 15 psig)

Supply Piping

Machine sizes 16JB077 thru 16JB124 have

steam supply inlets on each end. These are to be
considered as two generators and should be piped
from a common steam header as in multiple
machine installations (see Fig. 2). Each inlet should

then be piped in accordance with Fig. 1.

HEADER FOR

N0.2 END

NOTES:

1. Piping appiies to moitipie macbiries connected in paraiief

(3 shown).

2. Each end most be consdered as a separate generator.

3. The feed to each end of each generator should be piped as

shown in rig. 1.

Fig. 2 — Steam Piping For 16JB077 thru 124

Steam piping to the absorption machine should

be designed and supported to allow for thermal
expansion without imposing undue stresses on the
generator inlet. The machine is not designed for,
nor expected to act as, a piping support or anchor
for withstanding thermal stresses.

Condensate Systems

— Satisfactory operation of

the absorption machine requires a condensate
handling system designed with the specific char-
acteristics of the absorption machine in mind. The
following is intended to supplement available
reference data on condensate systems such as
Carrier System Design Manual, ASHRAE Guide

and individual manufacturer’s recommendations.
ATMOSPHERIC

CONDENSATE

RETURN

SYSTEMS (VENTED) - These systems usually
consist of steam traps, vented receiver, condensate
pump, and condensate cooler. Fig. 3 illustrates
typical atmospheric condensate return systems. On
larger machines, with dual steam generators, the

condensate outlet from each generator must be

piped thru separate steam traps.

Trap Selection — Steam traps should be located as

far below the generator outlet as possible. Actual
pressure drop available for trap selection will
depend on exact trap location below the generator