Installation, Continued), 3 – electrical operation – Winco ASCO 300 D Design 30-230 Amp User Manual

Page 8: Transfer test

background image

INSTALLATION

(continued)

1--5

Press until light

FLASHES

Press for 15 Seconds

TRANSFER SWITCH TEST

BYPASS TIME DELAY

SET ENGINE EXERCISER

observe these lights

press this button

Figure 1–6. Standard controls and indicators.

3 – Electrical Operation

This procedure will check the electrical operation of the

Automatic Transfer Switch. See Figure 1–6.

Close the enclosure door first !

!

Transfer Test

Both normal and emergency sources must be available

and the emergency source generator (if used) must be
capable of being started in this procedure.
Perform steps 1 through 8 at the right. Observe the status

lights. See Figure 1–6.

Black circle means light is on.

White circle means light is off.

NOTE: If Motor Load Transfer feature

is activated, then transfer may not occur

immediately after the respective time
delays. Transfer will only occur when

the phase relationship between sources

is correct.

This completes the Functional Test of the ASCO Series 300
Automatic Transfer Switch. Leave the engine–generator

starting control in the automatic position.

1

The normal source must be

available and the generator

must be ready to start.

Check that the

Normal Source

Available light is on.

2

Press and hold the

Transfer

Switch Test button until the

engine starts and runs. This

should happen within 15 sec.

TRANSFER SWITCH TEST

3 The Emergency Source

Available light should come on.

4

The transfer switch should

transfer to the Emergency

position. The

Load Connected

to Emergency light should come

on and the

Load Connected to

Normal light should go off.

5

If the

transfer to emergency

delay is used the transfer

should occurs after a time delay

(up to 5 minutes).

For immediate transfer press

the

Bypass Time Delay button.

BYPASS TIME DELAY

6

The transfer switch should

transfer back to the Normal

position. The

Load Connected

to Normal light should come on

and the

Load Connected to

Emergency light should go off.

7

If the

retransfer to normal delay

is used the retransfer should

occur after a time delay

(up to 30 minutes).

For immediate retransfer press

the

Bypass Time Delay button.

BYPASS TIME DELAY

8

The

unloaded running delay

keeps the generator running for

5 minutes (cool–down period).

Then the generator should stop

and the

Emergency Source

Available light should go off.