INSTALLATION

(continued)

1--4

Press until light

FLASHES

Press for 15 Seconds

TRANSFER SWITCH TEST

BYPASS TIME DELAY

SET ENGINE EXERCISER

observe these lights

Figure 1–5. Standard controls and indicators.

2 – Voltage Checks

First check nameplate on transfer switch; rated voltage

must be the same as normal and emergency line voltages.

Verify that the feeders have been

connected to the proper lugs.

!

Use extreme caution when using a meter

to measure voltages in the following

steps. Do not touch power terminals;

shock, burns, or death could result !

Perform steps 1 through 6 at the right. Observe the status

lights. See Figure 1–5.

Black circle means light is on.

White circle means light is off.

* If necessary, adjust voltage regulator on the generator
according to the manufacturer’s recommendations. The

Automatic Transfer Switch will respond only to the rated

voltage specified on the Transfer Switch nameplate.
Also see page 4–1 for the HI–LOW voltage adjust setting

in the controller. The LOW setting shifts all voltage

settings down 4.2%; for example, 240 V to 230 V.

1

Close the normal source circuit

breaker. The

Load Connected

To Normal and the Normal

Source Available lights should

come on.

2

Use an accurate voltmeter to

check phase to phase and

phase to neutral voltages

present at the transfer switch

normal source terminals.

3

Close the emergency source

circuit breaker. (Start generator,

if necessary.) The

Load

Connected To Normal and the

Emergency Source Available

lights should come on.

4

Use an accurate voltmeter to

check phase to phase and

phase to neutral voltages

present at the transfer switch

emergency source terminals.*

5

Use a phase rotation meter to

check phase rotation of

emergency source; it must be

the same as the normal source.

A B C

6

Shut down the

engine–generator, if applicable.

The

Emergency Source

Accepted light should go off.

Then put the starting control

selector switch (on the

generator set) in the

automatic

position. Close enclosure door.