10 Software Setup

1. Start up your sprayer and test the sprayer’s functionality. The display terminal does not need

to be powered on for the original boom function switches to operate. Unfold the booms and
raise/lower each boom and the main section.

Confirm that the cabling and hoses are agreeable to the entire range of motion.

2. If any functions do not work, review the hydraulic and electrical portions of this manual to

check for proper installation.

3. Turn on the power for the display terminal using the switch on the side.

4. The procedure for the installation of the UC5 Spray Height Control system is now complete.

Begin the AUTOMATIC SYSTEM SETUP procedure as described in the UC5 Spray Height
Control Operator’s Manual.

5. For optimal performance of the UC5 system, there should be very little play at the hitch

clevis. The addition of polymer washers can help tighten up this connection (Figure 23).

Figure 23: Hitch Point