10. Install the square DIN connectors from

C03 onto each NORAC valve as shown
in Figure 23. The connectors on C03
are marked RIGHT UP, LEFT UP,
RIGHT PORT
(“right down”), and
LEFT PORT (“left down”). Fasten
with the included rubber seals and
screws. Ensure that the cables are
oriented as shown, with the cable labels
RIGHT PORT and LEFT PORT on
the SAME side as the “port-side” of the
block

Figure 23 – Valve Cable Connections

11. Connect the CAN Node cable (C02B) to

the 4-pin AMP plug on C11.

12. Route the CAN Node cable (C02B) to

the roll sensors. Follow existing cables
and/or hydraulic lines.

13. Connect the sensor branch cable (C02)

to the 4-pin AMP plug on C02B .

14. Route the sensor branch cable (C02) to

the wing and main sensors. Follow
existing cables and/or hydraulic lines
along the boom.

15. Cable-tie the installed cables every 12

inches.

IMPORTANT:

Provide enough slack in all cables to
account for the movement of the main
section, parallel lift, and FOLDING boom
movement.