NORAC UC4+BC+NT3 User Manual
Page 24
21
5. There is an access hole located in the
front right corner of the cab floor that
can be seen when the floor mat is
lifted. Access plates (B16, B17 and
B18) which maintain the cab seal are
provided in the UC4+ kit. Rout C01
and C10 through the small hole and
large hole in the access plate (Figure
2 and Figure 20).
Leave the cover plates (B17 and
B18) unscrewed at this point.
Figure 20: Access plates
configurations
Figure 21: Valve Cable configurations
Outside of Cab
6. Connect the 6-pin shroud of the valve
extension cable (C04) to the 6-pin
tower of C10.
The valve extension cable (C04)
is packaged with one end not
installed. This is for installation
on other sprayer types. Install
the included connector as per the
drawing in Section 5.5. If you
make a mistake use the pin
pusher tool supplied to remove
the wires.
7. Route C01 and C04 to the front of the
sprayer, in the vicinity of the valve
block.
8. Connect the 6-pin tower on the valve
cable (C03) to the mating 6-pin shroud
on C04.
If your sprayer has the quick
disconnect option, also install the
valve disconnect cable (C11)
betweenC04 and C03.
9. Install the 2-pin connectors from C03
onto each NORAC valve as shown in
Figure 22.
10. The connectors on the valve cable
(C03) are marked RIGHT UP, LEFT
UP, RIGHT DOWN and LEFT
DOWN. Cables labeled with UP go
on the same side as the hydraulic hoses.
Figure 22: Valve Cable Connections