work into place along the

fillers, start at one end and

Note: When attaching pocket

CONTINUOUS POCKET

Prestage necessary tools and materials in the work area. Prepare all head,
sill, and jamb substrates by cleaning and setting all flashings and/or
membrane seals as specified by the project shop drawings.
Insert the mullion and/or head anchor, as specified by the project
shop drawings, into the end of tubular mullions. For splice joints and floor
anchors at multispan conditions, refer to steps #2 and #3 on pages 4

SEE APPROVED
SHOP DRAWINGS
FOR DIMENSION.

PERIMETER WITH

FILLER

and 5.

remaining length.

SIZE AND LOCATE ALL
BOLTS BASED ON JOB
CONDITIONS AND STRUCTURAL
REQUIREMENTS.

SHIM UNDER VERTICAL
MULLION.

MULLION ANCHORS

AT HEAD CONNECTION

TOP ANCHOR IS REQUIRED

FOR THERMAL MOVEMENT.

VERTICAL MULLIONS.

MULL ANCHOR AT INTERMEDIATE

"F" ANCHOR

STEP #1 INSTALL VERTICAL MULLIONS AND ANCHORS

SECTION II: VERTICAL FRAME INSTALLATION