Performance Verification
14. Slightly depress the bleed valve on the left line regulator to create a small flow of gas through the manifold.
15. Verify the pressure gauge reading on the bank “In Use” regulator to see if it is set up as per the specified pressure
setting. If the pressure is not correct, refer to the bank regulator pressure adjustment procedure.
16. Verify that the line pressure gauge reading is the same as in step 9. If the pressure is not correct, refer to the Line
regulator pressure adjustment procedure.
17. Watch the pressure gauge readings on the left bank regulator and the supply line for at least five minutes to
ensure the readings do not continue to increase.
18. Close all cylinders on the left side of the manifold. Depress the bleed valve slightly so that the left bank high
pressure gauge drops slowly. Verify that the manifold switches to the right bank when the left bank high pressure
gauge drops below the specified setting of the bank regulator.
19. Verify only the right bank Green “In Use” LED and the left bank Red “Empty” LED are illuminated..
20. Slowly open a cylinder on the left side. Verify that the left bank Red “Empty” LED goes out and the left bank Yellow
“Ready” LED illuminates.
21. Open both of the right side line regulator ball valves.
22. Close the left and right side cylinders.
23. Record the pressure readings of the left and right bank cylinder content gauges.
24. Verify after 15 minutes that the pressure reading on the gauges has remained the same.
25. Slowly open all cylinders on both banks of the manifold.
26. Using the switches on the circuit board, switch the manifold to the bank of cylinders with the least pressure.
27. Reinstall the manifold control panel cover.
28. Open the 3/4” source (line) shut-off valve.