Performance verification – Amico Dome Loaded Manifold NFPA User Manual
Page 22

22
Amico Pipeline
Performance Verification
Use the following test steps to verify the manifold’s functional performance:
1. Remove manifold cover.
2. Before beginning the test, verify following:
• If the manifold is not in use, close the 3/4” source shut-off valve.
• Verify that the two right-side line regulator isolation valves are open and the two left-side line regulator
isolation valves are closed.
3. As a starting point for this procedure, set the manifold to have the right bank as In Use. If the right bank Green LED
is illuminated, proceed to the next step. If the left bank Green LED is illuminated, manually switch the manifold
to the right side by pressing the left switch on the control board.
4. Verify that the right bank Green LED “In Use” and the left bank Yellow “Ready” lights are illuminated.
5. If the manifold is connected to a master alarm panel, verify that the manifold switchover alarm is not activated.
6. If the manifold is equipped with a pilot regulator, verify that its gauge reads 50 PSI.
7. Verify the gauge reading for the “In Use” right bank regulator. If the pressure is not correct, refer to the bank
regulator pressure adjustment procedure.
8. Verify the line pressure gauge reading. If the pressure is not correct, refer to the line regulator pressure
adjustment procedure. Note the reading for later use.
9. Watch the pressure gauge readings of the right side bank regulator and the line pressure gauge for at least five
minutes. Readings may be slightly higher without vent flow but verify the readings do not continue to increase.
10. Close all cylinders on the right side of the manifold. Use the bleed valve on the line regulator to slowly vent off
pressure until the right bank high pressure gauge drops. Verify that the manifold switches to the left bank when
the right bank high pressure gauge drops below the specified setting of the bank regulator.
11. Verify that only the left bank Green “In Use” LED and the right bank Red “Empty” LED are illuminated.
12. If the manifold is connected to a master alarm panel, verify that the switchover alarm is activated.
13. Close the right-side line regulator ball valves and open the left line regulator ball valves.