Preparation and Setup

Agitation & Gauge Plumbing

Refer to Figure 9

1.

Assemble a section of 1" hose (1) on to the agitation
hose barb (2). Route the hose along the other two
hoses assembled in Figure 6 on page 16.

2.

Place the 1" hose barb elbow (3) so that the vertical
section of the 1" hose guard material {Figure 6 (14)}
that secures the other two hoses {Figure 6 (10) &
(12)} assembled vertically along the side of the tank.

3.

Secure the hose to the hose barbs with the number
16 hose clamps. After all the hoses are routed
through the hose guard material {Figure 6 (14)}, fold
the ends of the hose guard material back under-
neath and tie with cable ties {Figure 6 (6)}.

4.

Attach the tee assembly (4) to the vertical 1" hose.

5.

Measure and cut two pieces of hose 3/4" (5) so that
they are assembled from the tee assembly (4) to the
agitation elbow (6) on both tanks. Secure the num-
ber 12 hose clamps on the 3/4" hose.

6.

Cut a section of 3/8" hose (7) to a length that is sat-
isfactory for where you will place the gauge on the
tractor. Route the hose from the 3/8" hose barb on
the solenoids to the 3/8" hose barb on the gauge as-
sembly as shown. Secure the hose with the number
5 hose clamps.

Figure 9

Agitation Assembly

12595

This manual is related to the following products: