Operation, Pre-operational checklist, Auger drive & lockout procedure – Wheatheart WHR 130 x 51-71ft Augers PTO User Manual
Page 39
![background image](/manuals/598584/39/background.png)
WHEATHEART - GHR & WHR GRAIN AUGERS
5. O
PERATION
GRAIN AUGERS SD
5.1. P
RE
-O
PERATIONAL
C
HECKLIST
30662 R1
39
5. Operation
5.1. PRE-OPERATIONAL CHECKLIST
Before operating auger each time, the operator must confirm the following:
• All fasteners are secure as per assembly instructions.
• PTO driveline is connected and secure.
• PTO driveline shield rotates freely.
• Lift cable is not frayed or damaged.
• Lift cable is properly seated in cable sheaves.
• Cable clamps are secure.
• Tube alignment is reasonably straight.
• Auger wheels are chocked, and if necessary, tractor wheels are chocked
or the parking brake has been engaged.
• Intake area and discharge spout are free of obstructions.
• Proper maintenance has been performed.
5.2. AUGER DRIVE & LOCKOUT PROCEDURE
Warning: Before continuing, ensure you have read and understand the relevant information
in the safety section. Safety information is provided to help prevent serious injury, death, or
property damage.
Drive
Type
Before Operation
Lockout
PTO
Driveline
Before starting, ensure:
• PTO driveline is securely attached to
the tractor and gearbox
• tractor park brake in engaged and/or
wheels are chocked
• you are not exceeding the maximum
operating length of 92” (2337 mm) of the
PTO driveline or maximum angle of 15°
• PTO drive on the tractor is in the off
position
Shut off tractor’s engine and
remove key from tractor.
• If removing key is impossible,
remove PTO driveline from trac-
tor.