4.18

Underground Installation Methods

Submarine Installation

Floor Surface Placement

In this method of construction, the conduit is placed on the floor of the body of water. Conduit must be weighted to
increase its displacement volume to overcome the effects of buoyancy.

This chart lists the displacement volume for ConQuest conduits.

This chart lists the weight per cubic foot of water the conduit displaces.

Water Type

Pounds per Cubic Foot

Fresh 62.43
Salt 63.99

Conduit Size

Displacement Volume

1 inch

.0094 cubic feet

1.25 inches

.0150 cubic feet

1.50 inches

.0197 cubic feet

2 inches

.0308 cubic feet