beautypg.com

Titus Horizontal Basic IOM User Manual

Page 3

background image

3


6.2

All electric wiring is properly routed, secure and capped.


6.3

The filter, where provided, is clean and secured in its position.



7.

INITIAL START-UP


7.1

Chilled/Hot Water Unit


7.1.1

Ensure that the main distribution system is operable (i.e. both supply and return piping
are under full operating pressure).


7.1.2

Open the unit’s isolating ball valves (optional) and observe that no leaks are evident.


7.1.3

Open the 2-Way or 3-Way Valve (optional) manually by moving the lever provided on
the valve motor thus pressurizing the unit’s coil.


7.1.4

Remove the cap of the air-vent valve and depress the needle to release the trapped air.
Continue until only liquid is coming through, then re-cap and secure tightly.