Commissioning report – Schwank SEB(U) User Manual
Page 27
SP-MSEB-BX-10A
SEB Manual
RD: JUNE 2004
RL: 10
KH
22. START-UP SHEET
Page 23
COMMISSIONING REPORT
CONTRACTOR NAME: ................................................................................DATE................................
ADDRESS:............................................................................................................................................
............................................................................................................................................................
CITY:........................................................................................
PHONE:...................................................................................
CELL: .....................................................................................
JOB SITE......................................................................................................CITY................................
HEATER MODEL NUMBER:.................................................................................
HEATER SERIAL NUMBER: ................................................................................
FAX COMPLETED FORM TO TECHNICAL SERVICES: CANADA - 905-712-8336 USA - 706-554-9390
START-UP NEEDS TO BE COMPLETED BY THE LICENSED GAS INSTALLER.
ALLEVIATE NUISANCE CALL BACKS FOR THE CONTRACTOR, THE FOLLOWING
A CONTRACTOR IS CALLING FOR TECHNICAL SUPPORT,
MUST PROVIDE THE FOLLOWING INFORMATION
FROM HIS COMPLETED COMMISSIONING REPORT ON NEXT PAGE
AS PER I&O MANUAL AND LOCAL CODES
IT IS NOT A PLUG IN APPLIANCE..IT DOES REQUIRE COMMISSIONING AND FIELD ADJUSTMENTS
THIS EQUIPMENT HAS BEEN FACTORY FIRED AND TESTED BEFORE DELIVERY, NEVERTHELESS
TO ENSURE THAT SITE CONDITIONS ARE COMPATIBLE WITH THIS HEATER, AND TO