22. START-UP SHEET

Page 23

COMMISSIONING REPORT

CONTRACTOR NAME: ................................................................................DATE................................

ADDRESS:............................................................................................................................................

............................................................................................................................................................

CITY:........................................................................................

PHONE:...................................................................................

CELL: .....................................................................................

JOB SITE......................................................................................................CITY................................

HEATER MODEL NUMBER:.................................................................................

HEATER SERIAL NUMBER: ................................................................................

FAX COMPLETED FORM TO TECHNICAL SERVICES: CANADA - 905-712-8336 USA - 706-554-9390

START-UP NEEDS TO BE COMPLETED BY THE LICENSED GAS INSTALLER.

ALLEVIATE NUISANCE CALL BACKS FOR THE CONTRACTOR, THE FOLLOWING

A CONTRACTOR IS CALLING FOR TECHNICAL SUPPORT,

MUST PROVIDE THE FOLLOWING INFORMATION

FROM HIS COMPLETED COMMISSIONING REPORT ON NEXT PAGE

AS PER I&O MANUAL AND LOCAL CODES

IT IS NOT A PLUG IN APPLIANCE..IT DOES REQUIRE COMMISSIONING AND FIELD ADJUSTMENTS

THIS EQUIPMENT HAS BEEN FACTORY FIRED AND TESTED BEFORE DELIVERY, NEVERTHELESS

TO ENSURE THAT SITE CONDITIONS ARE COMPATIBLE WITH THIS HEATER, AND TO