Outrigger installation, Outrigger installation -6 – JLG 41AM Operator Manual User Manual
Page 50

SECTION 4 - MACHINE OPERATION
4-6
– JLG Lift –
3121211
Outrigger Installation
NOTICE
AS A SAFETY PRECAUTION, DUE TO DIFFERENT LENGTHS, OUTRIGGER BEAMS
ARE DESIGNED TO FIT A SPECIFIC MODEL AND ARE NOT INTERCHANGEABLE.
1. Remove one outrigger beam from the stowage socket.
2. Insert outrigger beam into an outrigger socket on the
base frame with outrigger interlock contact on the
bottom. Push outrigger beam in socket until locking
pin on side of outrigger socket snaps into the outrig-
ger beam detent. Repeat for remaining outriggers.
3. With all outriggers inserted, turn each outrigger jack
down, lifting entire machine until all wheels are off the
ground.
4. When all four (4) wheels are off the ground, use the
bubble level on the base frame to level machine.
NOTICE
MACHINE WILL OPERATE ONLY IF ALL FOUR (4) INTERLOCK LED LIGHTS ARE
ILLUMINATED.