JLG 4017PS Operator Manual User Manual
Page 135

Section 5 - Attachments and Hitches
5-43
31200753
To control mixer:
The attachment auxiliary hydraulic roller switch (3) controls the bucket mixer.
• Push roller switch down to rotate rearward.
• Push roller switch up to rotate forward.
Installation Procedure:
• Refer to “Attachment Installation” on page 5-11.
Operation:
• Close bucket gate, level bucket and fully retract and lower boom to load material.
• Distribute material evenly within the bucket. Bucket capacity charts are for evenly
distributed loads only.
• Load center will vary depending on the amount of material in the bucket. Always
ensure compliance with the capacity chart.
• Travel in accordance with requirements set forth in Section 1 - General Safety
Practices.
• Position bucket and open bucket gate to release load.
Equipment Damage Precautions
• Transport the concrete bucket as low as practical at a slow speed and without
rapid side to side movement.