xI Start-up and Checkout

Use the following procedure for initial start-up of the boiler:

1) If not already done, flush the system to remove sediment, flux, and traces of boiler additives. This should

be done with the boiler isolated from the system.

2) Fill the boiler and hydronic system with water meeting the following requirements:

pH between 6.5 and 8.5

Total Solids less than 2500 PPM

Hardness less than 120 PPM (7 Grains/Gallon)

Pressurize the system to at least 12 psi at the boiler

3) Check all new piping for leaks and purge piping sections that are filled with air. See the National Fuel Gas

Code for additional information on testing and purging gas lines.

4) Vent system must be complete and free of obstructions before attempting to fire boiler. Make sure that the

silicone cure time called for in the vent assembly instructions has passed before firing boiler.

5) Inspect all line voltage wiring for loose or uninsulated connections.
6) Remove the dust cap from the condensate trap (Fig 6.11). Add water to the trap until water runs out the

condensate drain. Reinstall the dust cap.

NOTE

safE lIghTINg aND OThEr PErfOrmaNCE CrITErIa wErE mET wITh ThE gas

TraIN assEmbly PrOVIDED ON ThE bOIlEr whEN ThE bOIlEr uNDErwENT

ThE TEsT sPECIfIED IN Z21.13.

warNINg

IF ANTIFREEZE IS ADDED To THE SySTEM, uSE oNE oF THE FoLLoWING

APPRoVED PRoDuCTS oR THEIR EquIVALENT:

FERNox ALPHI-11

GE-BETZ SENTINEL x500

NEVEr aTTEmPT TO fIll a hOT EmPTy bOIlEr.

warNINg

NEVER uSE A FLAME To CHECk FoR GAS LEAkS.

MAkE SuRE THAT THE AREA ARouND THE BoILER IS CLEAR AND FREE

FRoM CoMBuSTIBLE MATERIALS, GASoLINE AND oTHER FLAMMABLE

VaPOrs aND lIquIDs