Installation
• Puddle with a vibrator.
• Pump the grout into place.
5. Allow the grout to set.
1. Baseplate
2. Shims or wedges
3. Grout
4. Foundation
5. Sleeve
6. Dam
7. Bolt
6. Fill the remainder of the baseplate with grout, and allow the grout to set for at least 48
hours.
1. Baseplate
2. Grout
3. Foundation
4. Dam
5. Bolt
7. Remove the leveling jackscrews after the grout hardens in order to remove any stress
points.
8. Tighten the foundation bolts.
9. Recheck the alignment.
26
Model 3640 Installation, Operation, and Maintenance Manual
See also other documents in the category Goulds Pumps Pumps:
- 3100 - IOM (52 pages)
- 3171 - IOM (60 pages)
- 3180-86 - IOM (158 pages)
- 3189 - IOM (32 pages)
- 3196 - IOM (148 pages)
- 3196 i-FRAME - IOM (152 pages)
- 3198 i-FRAME - IOM (126 pages)
- 3296 EZMAG - IOM (96 pages)
- 3296M - IOM (92 pages)
- 3298 - IOM (120 pages)
- 3311 - IOM (44 pages)
- 3316 - IOM (36 pages)
- 3335 - IOM (40 pages)
- 3355 - IOM (66 pages)
- 3393 - IOM (124 pages)
- 3408 - IOM (78 pages)
- 3408A - IOM (44 pages)
- 3409 - IOM (68 pages)
- 3410 - IOM (56 pages)
- 3420 - IOM (120 pages)
- 3498 - IOM (59 pages)
- 3500XD - IOM (44 pages)
- 3501 Mixer - IOM (48 pages)
- 3600 - IOM (110 pages)
- 3610 - IOM (98 pages)
- 3620 - IOM (98 pages)
- 3642 - IOM (12 pages)
- 3675 - IOM (12 pages)
- 3700 - IOM (110 pages)
- 3755 - IOM (32 pages)
- 3796 i-FRAME - IOM (134 pages)
- 3910 11th ed. - IOM (80 pages)
- 3935 - IOM (24 pages)
- 3996 - IOM (52 pages)
- 4550 - IOM (36 pages)
- 5000 - IOM (24 pages)
- 5100 - IOM (28 pages)
- 5150 - IOM (28 pages)
- 7200CB - IOM (132 pages)
- ANSI FAMILY IOM (ATEX Compliant) (56 pages)
- ANSI FAMILY IOM (ATEX Compliant) (27 pages)
- ANSI FAMILY IOM (ATEX Compliant) (42 pages)
- ANSI FAMILY IOM (ATEX Compliant) (45 pages)
- Pump Safety (9 pages)