User Guide APC Silcon 480kW 400V UPS

990-4058

Maintenance & Testing

6.0 Maintenance & Testing

UPS maintenance should be carried out by trained service engineers only. Service and
maintenance contract is recommended.

6.1

Fan

It is recommended to replace fans every 3 years.

6.2

Battery Monitoring Test

Systems with built-in batteries have a standard battery monitoring feature (optional in other
systems).

Battery Test Results:

1. Battery OK. Back-up time normal.

2. Reduced battery capacity - “Battery weak” message appears.

3. Battery capacity too low - “Battery defective” message appears.

Carry out battery monitoring test by discharging max. 25% of battery energy. For systems with
no battery monitor/no excess back-up time, a battery capacity test is recommended every 6
months.

Carry out battery tests when load is least affected.

6.3

Battery Capacity Test

CAUTION!

Allow 16 hours to restore full back-up time after battery capacity tests.