Main frame roller installation, Set-up of frame -3 – 2-13, Figure 1 2-3 – Summers 84' Superroller User Manual
Page 13
SECTION 2 - ASSEMBLY
DETAIL A
A
9LR6242_CENTER
2/23/2011
9LR6242.iam/
AFTER DRUM IS INSTALLED
PLACE STANDS AT THE 4
LOCATIONS SHOWN TO
STABILIZE FRAME.
8P4215
8X0265
3/4" LN
8X0306
3/4" LW
8P5080
8X0111
3/4" X 2-1/2"
8R8005
8R8010
(42" DIA.)
8P4203 (36" DIA.)
Block
Frame at
arrows
Figure 1
2-3
Main Frame Roller Installation (Instructions for both 62’ & 84’)
(NOTE: 62’ shown in drawings)
MF1. Position 8P4215 on a flat even surface; block the roller to avoid unexpected movement.
CAUTION: The 15’ roller weighs 4285 lbs., use extreme care when moving rollers and frame
components.
NOTE: An H has been stamped onto one end of each roller. Position the center
roller with the H to the left. All other rollers should have the H positioned to the center of the
machine.
MF2. Use a fork lift or crane to position the main frame 8P7120 over the center drum and lower the
frame so the roller axle stubs fit between the bearing hangers as shown in the Figure 1.
MF3. Install bearings with the
grease zerk toward the rear of the machine. Secure to bolt plates
with the hardware shown. Install reinforcement angles between the bottom attachment hole
on the inside of the bolt plate, as shown in Figure 1.
MF4. Install snap rings on each roller shaft. Ensure that the roller is centered in the bearings and
tighten the set screws.
MF5. Before removing the lifting device for the main frame, block the frame in the locations shown
in Figure 1, also install blocks under the roller to keep it from rolling.
Block
Frame at
arrows