INSTALLATION INSTRUCTIONS
for Fiberglass Gliding Patio Doors with Applied Nailing Fin (JII104)
3
1
REMOVE PACKAGING AND INSPECT PATIO DOOR
2
INSPECT ROUGH OPENING
REMOVE PACKAGING
Remove shipping materials such as corner covers, shipping blocks or
pads. Remove any temporary handles just prior to installation into the
rough opening.
INSPECT PATIO DOOR
• Cosmetic damage
• Product squareness (diagonal measurements must be within 1/4"
difference)
• Verify the width and
height of the patio
door are each
1/2"- 3/4" smaller
than the rough
opening width/
height. Mulled
units should be 3/4"
smaller.
• Verify the rough
opening is square.
The (A) and (B)
measurements
should be the same.
Maximum allowable
deviation from square
is 1/4".
• Correct product (size, color, grid pattern, handing, glazing, energy-
efficiency requirements, etc.)
• For side-by-side mulled units, a drip cap that extends the length of the
frame plus 1/8" overhang on each end is required.
If any of the above conditions represent a concern, or if you expect
environmental conditions to exceed the patio door's performance
rating, do not install the patio door. Contact your dealer or distributor
for recommendations.
Verify Square, Level, & Plumb
A
B
D
C
E
• Verify the rough opening is level and plumb (C) and (D). The
maximum allowable deviation is 1/8".
• The rough opening sill must not be crowned or sagged (D). A 5
degree
sloped sill is recommended.
• The exterior face of the rough opening must be in a single plane (E)
with less than 1/8" twist from corner to corner.
• Minimum double studs should be used at all wood framed rough
openings.
• The header must be supported by trimmer studs.
3
PREPARE SILL PAN
1. Cut a piece of sheet
material to the
length shown.
2. Lightly crease folding
lines 1/2" in from the
two short sides and
one long side.
3. Measure the width of
the frame from the
interior to the nailing
fin slot and add
9/16".
4. Take this distance
from the back edge
and lightly crease a
folding line across
the sheet material.
5. For step-down
landings, cut 1/2" in
at the folding line
on both sides of the
sheet material.
6. For continuous slab,
cut across the folding line.
For continuous
slab, remove flap
Measure
frame
width
Jamb fin
slot
Interior
Frame width
+9/16"
Length of rough opening sill plus 1"
Folding line
1/2"
1/2"
7. Fold the three back
sides up to make a
3-sided box, and, for
step-down landings,
fold the front flap
down.
Fold sides and back up
Fold corner
forward
Fold front
flap down