Installing the scsi interface cable, Installing fiber interface cables – HP Integrity NonStop H-Series User Manual
Page 37
![background image](/manuals/397191/37/background.png)
Cabling the Fibre Channel Converter
9800FC (CT9800FC) Fibre Channel Converter Installation and User’s Guide— 524957-003
3 -9
Installing the SCSI Interface Cable
Installing the SCSI Interface Cable
1. Before you install the 68-pin SCSI cable from the Fibre Channel converter to the
server, check that the tape library and the Fiber Channel converter are both
powered off. Refer to
Appendix A, Multimode Fiber Optic Cables
for a listing of
SCSI part numbers.
2. Connect the 68-pin SCSI cable to the SCSI channel port on the Fibre Channel
converter. See
Figure 3-2, Rear Panel Components,
3. Connect the other end of the 68-pin SCSI cable to a supported SCSI port on a
NonStop S-series server.
Installing Fiber Interface Cables
1. Connect one end of the fiber cable to the Fiber Channel interface card. See
2. Connect the other end of the cable to the GBIC on the Fibre Channel converter.
Figure 3-5, Location of the GBIC on the Fibre Channel Converter,