Mechanical
joint
The exit point of the conduit
must be completely embedded.
Concrete slab
4'' (101 mm) to 6'' (152 mm)
Mechanical joint
minimum 6'' (152 mm)
inside the surface
to be heated
Distance between the top of the cable
and the finished surface of the coating
Minimum: 2'' (50 mm)
Maximum: 3.5'' (89 mm)
Wire mesh
Compacted and drained
granular base
Plastic tie-wraps
Sand base
Expansion joint
Compacted
and drained
granular base
Compacted and
drained granular base
Detached cable
Heating cable
Concrete slab
Concrete slab
Control joint
Maximum depth
1'' (25 mm)
Angle iron
1'' x 1''
Figure 9: Concrete coating
Figure 10: Bypass of expansion joint
Figure 11: Crossing a control joint
Do not roll over uncovered cables with any equipment.
Special precautions should be taken while walking over the cable
and while handling sharp tools during the installation process.
CAUTION!
Work stages should be planned so the cable does not remain
uncovered between the installation and the coating stages.
Where the project encounters any delay between these stages,
special precautions should be taken to mechanically protect
the cable against any breakage.
CAUTION!