3.4

Procedure – Installing the Focus

TM

Probe:

1. Ensure the Ball Valve is in the OFF position. (Handle perpendicular to Ball Valve as shown)

2. Loosen the Packing Gland Nut to allow the probe to slide through.

3. Slide the probe through the Packing Gland until it gently rests against the closed ball valve. (An

o-ring in the packing gland will seal against the probe body)

4. Connect the Quick Link and Safety Chain to the Safety Chain Clip.

5. Adjust length of Safety Chain until it is tight.

6. Orient probe flats parallel to flow direction as shown in Figure 8.

7. Turn the ball valve to the ON position. (Handle parallel to Ball Valve)
8. Push the probe through to the quarter radius depth marked in Procedure 3.2 or center point marked

in Procedure 3.3 as applicable.

9. Tighten the Packing Gland Nut to 55-60in-lbs to ensure solid retention.





Figure 7: Inserting the Probe into the Pipe Fittings

*

*

A purge nipple may be added as needed by the customer during installation of the flow meter. This would

allow for safe expulsion of gases trapped between the ball valve and packing gland seal during removal.

FOCUS

TM

PROBE - OFM

CLAMP-ON COLLAR

PACKING GLAND NUT

NOTE:

Ensure the probe is oriented so
that the cutout in the probe is
parallel to the flow direction in

the pipe. Use the flat surface of
the Fiber connector as a visual
reference and DO NOT allow the

probe to rotate once orientation is
established.

NOTE:

DO NOT REMOVE PLUG

WHILE BALL VALVE IS IN

THE OPEN POSITION

¼” NPT port for optional

purge nipple*