1.0 Focus

TM

Probe Pipe Fitting Installation

The instructions that follow are for installing the necessary fittings that will support the Focus

TM

Probe flow meter. Figure 1 shows the components and may be used as a visual reference while installing
the fittings. The Focus

TM

Probe must never be installed in a vertical position where debris or moisture is

likely to settle on the optics. When installing into horizontal runs, position the fittings so that the probe
will be inserted at the 3 o’clock position. (Refer to

Figure 8

) Mounting the probe horizontally will

minimize window-cleaning maintenance. Ensure that there is sufficient room around the pipe to install
and remove the insertion probe.

1.1 Procedure – Installing Pipe Fittings

1. Choose the location in the pipe that you want to install the Focus

TM

Probe.

2. Install a Threadolet with a 1” NPT thread.

3. Apply an appropriate pipe sealant and thread the 1” to ¾” Adapter into the weldolet and tighten.

4. Apply an appropriate pipe sealant and, holding the Ball Valve so the mounting holes and lever

point away from the pipe, thread the ¾” Ball Valve on to the Adapter and tighten.

5. Turn the Ball Valve to the off position. (Handle perpendicular to Ball Valve as shown)

6. Slide the Safety Chain Ring over the threading of the Packing Gland.

7. Apply an appropriate pipe sealant and thread the ¾” NPT Packing Gland into the Ball Valve and

tighten.




Figure 1: Install Fittings as Shown in Diagram

PIPE

1” TO ¾” ADAPTER

¾” NPT ISOLATION VALVE

SAFETY CHAIN

¾” NPT PACKING GLAND

1” Threadolet

NOTE:

1) Apply sealant to NPT threads

before installing.

¾” CLAMP COLLAR