Parts List
Tools
Required
Part Number
Description
Quantity
Drill
6409-2200
/Vent Door GVD CAB ASSY
1
Saws
6409-2202
/Vent Door GVD WEIGHT ASSY
1
1004-0050
SCRW SM #14x1 HX W SL Tek Z
8
1004-7120
SCRW Lag 1/4x1-1/4 Zinc
8
Directions
1. Mark rough opening for vent door on wall. The
vent should be a minimum of 8.5" (21.6 cm)
from the ceiling. See Figure 2.
2. Cut rough opening to size as shown in Table A
above.
3. Install vent. Insure that vent is mounted squarely in opening
and oriented for the proper air flow direction. Screws are
provided for either mounting in wood framing (1004-7120) or
metal (1004-0050).
4. Install Weight Assembly.
5. Adjust Weight to desired setting.
6. See the Vent Performance Chart on page 2.
Part Number
Vent Size
Rough Opening
6609-2200
12.75” x 45.625 (32.38 cm x 115.89 cm)
13.5” x 46.5” (34.29 cm x 118.11 cm)
GRAVITY VENT DOOR
Installation
Table A
Air Flow
8.5" minimum
from
ceiling
Figure 2 – Vent Mounting
Figure 3 – Gravity Vent Door Front & Side View
Weight
Assembly
Cabinet
Assembly
Figure 1
Gravity Vent Door