Installation, 1 overview, 2 installation – Yokogawa PK200 User Manual
Page 14: 1 pipe mounting, 2 wall mounting, Installation -1, Overview -1, Pipe mounting -1, Wall mounting -1

IM 21B03D01-01E
3-1
3. INSTALLATION
3.
INSTALLATION
3.1 Overview
When installing the PK200 converter, see section 1.4
“Precautions for Installation Area.” For the ambient
environmental conditions of an installation place, see
section 2.2 “Standard Specifications.”
3.2 Installation
PK200 can be installed on a pipe using a mounting
bracket provided or directly installed on the wall.
Select either method, taking into account the installa-
tion space and service method.
3.2.1 Pipe Mounting
When this instrument is mounted on a pipe, use the
mounting bracket and U-bolt provided. The pipe dia.
available is 50mm (2-INCH) and the instrument can be
installed on either a horizontal or vertical pipe.
Pipe
PK200
Mounting bracket
F0301.EPS
Figure 3.1 Pipe Mounting
3.2.2 Wall Mounting
When the instrument is installed on the wall, use the
two M8 screws provided.
PK200
F0302.EPS
Figure 3.2 Wall Mounting