END OF DAY SHUTDOWN CHECKLIST FOR ULTRAMAX

ACTIVITIES MUST BE DONE IN THE SEQUENCE SHOWN, AND MUST BE TICKED OFF AS

COMPLETED. USE THIS CHECKLIST IN CONJUNCTION WITH THE OPERATING MANUAL FOR

THE ULTRAMAX UNIT. THIS SEQUENCE FOLLOWS ON FROM CHECKLIST 03 – SET UP

CHECKLIST

ACTIVITY

NO.

ACTIVITY

TICK WHEN
COMPLETED

Priority

Put on Respirator as specified for spray painting, Protective
Clothing, Eye Protection, and PVC Gloves

1

Flush the gun with solvent.

2

Wipe the face of the nozzle after flushing.

3

Turn off the air ball valve at the air intake.

4

Release the solvent flush tank pressure.

5

Remove the nozzle and clean it.

6

Remove the Mix Housing and clean it.

7

Wipe the gun block face with a clean rag.

8

Hang the gun with the gun block exit holes facing upwards.



ABNORMAL CONDITIONS OBSERVED AND CORRECTED

Abnormal Condition

a

a

a

a when
corrected



OPERATORS NAME: _______________________________________ DATE: ________________

SIGN OFF WHEN SHUT DOWN CHECKS ARE COMPLETED: _________________________