END OF DAY SHUTDOWN CHECKLIST FOR ULTRAMAX
ACTIVITIES MUST BE DONE IN THE SEQUENCE SHOWN, AND MUST BE TICKED OFF AS
COMPLETED. USE THIS CHECKLIST IN CONJUNCTION WITH THE OPERATING MANUAL FOR
THE ULTRAMAX UNIT. THIS SEQUENCE FOLLOWS ON FROM CHECKLIST 03 – SET UP
CHECKLIST
ACTIVITY
NO.
ACTIVITY
TICK WHEN
COMPLETED
Priority
Put on Respirator as specified for spray painting, Protective
Clothing, Eye Protection, and PVC Gloves
1
Flush the gun with solvent.
2
Wipe the face of the nozzle after flushing.
3
Turn off the air ball valve at the air intake.
4
Release the solvent flush tank pressure.
5
Remove the nozzle and clean it.
6
Remove the Mix Housing and clean it.
7
Wipe the gun block face with a clean rag.
8
Hang the gun with the gun block exit holes facing upwards.
ABNORMAL CONDITIONS OBSERVED AND CORRECTED
Abnormal Condition
a
a
a
a when
corrected
OPERATORS NAME: _______________________________________ DATE: ________________
SIGN OFF WHEN SHUT DOWN CHECKS ARE COMPLETED: _________________________