beautypg.com

Vent pipe requirements, Vent pipe installation, Indoor installation only) – John Wood Noritz N-069M_N-069S User Manual

Page 45

background image

45

8.

Vent Pipe Installation

• The first vertical run from the top of the heater

should be no longer than 3'.

• Make sure vent pipe is gas tight and will not

leak. Use silicon sealant wherever necessary.

• Do not common vent or connect more than

one appliance to this venting system.

• The total vent length including horizontal &

vertical vent runs should be no less than 3'.

• Do not place any dangerous objects at the end

of the exhaust vent.

• Steam (smoke) or water drops may come out

from the end of the exhaust pipe. Select the
location for the end of the vent so that steam is
not visible, and the vent is not wet with drip-
ping water.

• If snow is expected to accumulate, take care

the end of the pipe is not covered with snow or
hit by falling lumps of snow.

• Consult the vent pipe manufacturer's install-

ation instructions for chimney connections.

Appliance Adapters
• Use the following adapters to connect the

unit to the venting system.

Vent Piping
• Use only listed category III vent materials.
• Follow the vent pipe manufacturer's installation

instructions.

• Make the vertical section of the exhaust vent

as short as possible.

• Maintain the same vent pipe diameter from the

heater flue to the vent termination.

Pipe diameter

4"

No. of Elbows

Max. Straight Vent Length

3

15'

2

27'

1

39'

Clearances

Manufacturer and

Enclosed Unenclosed

Product

Hor. Vert. Hor. Vert.

Noritz N-Vent

4"

3"

3"

Protech FasNSeal

4"

3"

3"

Protech FasNSeal W2 6"

4"

3"

3"

HeatFab SafTVent

6"

6"

2"

2"

Z-Flex Z-Vent

8"

4"

1"

1"

Flex-L StaR-34

8"

4"

1"

1"

These clearances are subject to change.
Refer to the UL listing for the proper clearances.

Horizontal Vent Termination

• Terminate at least 12" above

grade or above snow line.

• Terminate at least 7' above a

public walkway, 6' from the

combustion air intake of any

appliance, and 3' from any

other building opening, gas

utility meter, service regulator

etc.

• Terminate at least 3' above any

forced air inlet within 10', 4'

below, 4' horizontally from or

1' above any door, window, or

gravity air inlet into any building

per National Fuel Gas Code

ANSI Z223.1/NFPA 54.

• Slope the horizontal vent 1/4"

downwards for every 12".

• Use a condensation drain if

necessary.

Appliance

Adapter

Elbow

Hanger

Straps

Wall

Thimble

Termination

3'

Max.

Slope vent

Downwards

(Indoor Installation Only)

8" (sides)

12"(top)

4"(bottom)

Manufacturer and

Product

Protech FasNSeal

FSAA4

HeatFab SafTVent

9401RYPK

Z-Flex Z-Vent

2SVWA04

Flex-L Star-34

SRASPSA4

Part No.

10" (sides)

15"(top)

6"(bottom)