5. Assembly

20

PNEG-1366 12" and 16" Series II Sweep Quick Disconnect Control Box Kit

Control Panel Installation

1. Remove the lock nut from the conduit hub. The conduit hub is factory installed on the conduit

assembly attached to the back base assembly.

2. Carefully inset the conduit hub, with wires, into the hole drilled during

Step 1 on Page 19

.

3. Install the lock nut on the hub and tighten.

4. Mount the control box to the back plate with the supplied hardware.

5. Use the supplied grounding lug (E160-1137) to properly ground the control box assembly to

the outlet.

Control Panel Receptacle Mounting (Current Style Panel)

Control Panel and Receptacle Installation

Open the control panel and mount it to the lift base panel assembly with the supplied hardware. There
are three (3) mounting positions on the lift base panel assembly in which to mount the control panel.

(See Figure 5C.)

Figure 5C

Electrical controls should be installed by a qualified electrician and must meet
standards set by the National Electrical Code and all local and state codes.

A main power disconnect switch capable of being locked only in the OFF position
should be used. The disconnect must be LOCKED in the OFF position before
unplugging either end of the power cord. This has been integrated into the control
panel after June 2010.

Electrical controls should be installed by a qualified electrician and must meet
standards set by the National Electrical Code and all local and state codes.

A main power disconnect switch capable of being locked only in the OFF position
should be used. The disconnect must be LOCKED in the OFF position before
unplugging either end of the power cord. This has been integrated into the control
panel after June 2010.