beautypg.com

Grain Systems Tanks PNEG-4105A User Manual

Page 19

background image

Chapter 2: General Overview

Guidelines for Construction Procedures and Lifting Jack Usage

The following procedure is a guideline when using the required lifting jack. Follow this general guideline
when lifting the bin as sidewalls are being installed.

NOTE: The roof and the top ring for odd ringed bins or the roof and two rings for even ringed bins, will be

installed prior to the beginning of bin lifting procedures. Refer to all other procedures on sidewall
and stiffener installation prior to the start of construction.

IMPORTANT: Begin building with the bin oriented for doors and material handling equipment to be in the

correct position when bin construction is complete.

1. Consider the starting location of the bin, relative to the location of doors and other accessories.

Proper placement of lifting jacks in relationship to anchor bolts could make a difference in final loca-
tions. Note that the sidewall sheets will be staggered.

2. The bin is lifted by the use of lifting jacks. Lifting jacks are used to slowly and evenly lift the bin during

construction. Lifting jacks must be properly sized and designed to carry all loads and job site condi-
tions associated with the construction of the bin..

The number of lifting jacks required is best determined by personal experience and expertise. Factors
such as bin size, jack design, construction conditions, support surface, etc., are all to be considered
when deciding how many to use. If in doubt, use one jack on every sheet. The lifting jack must be
adequate to carry all loads. Heavy duty jacks, generally hydraulic or electric powered in the case of
large bins, should be used for commercial installation. All jacks should be secured with braces or oth-
erwise maintained in a stable condition..

Lifting of the bins should not be done under windy conditions

Follow the jack manufacturers recommendations on capacity and operations.

3. Lifting brackets should be attached through the stiffener bolt holes. Normally you will need to attach

to at least four (4) bolts per stiffener.

4. Raise the bin just high enough to assemble the next ring. When lifting the bin, all jacks must lift at

an equal rate. Monitor the lift to ensure even lifting is occurring.

5. To the inside of the first ring, bolt the next ring. Be sure to stagger the sheets and select the proper

gauge material.

6. Lower the bin onto the foundation after assembling and tightening bolts on the new ring or rings.

7. Attach stiffeners to the body sheets every two (2) tiers (on the external surface of the bin). You may

want to leave sheets loose to make the attachment of the stiffeners easier.

8. Now re-bolt the lifting brackets to the lowest ring in place thus far. Continue ring additions by repeat-

ing Step 5 and Step 6.

9. Add inside and outside ladders as you continue to raise the bin. (Refer to the manual supplied with

the ladder.)

10.Lower the tank and secure to the foundation before leaving the job site.

11.At the completion of the tank, set stiffeners over the anchor bolts and measure the tank to ensure it is

in a round condition. Consult with GSI for questions on tolerances.

NOTE: For 2 ring doors or vehicle traffic doors, special placement issues may apply. Consult the special

instructions provided with two ring doors or vehicle traffic doors for these options.

Pneg-4105A 105 Ft Diameter 40-Series Bin

19