beautypg.com

Attaching the roof panels – Grain Systems Tanks PNEG-4105A User Manual

Page 118

background image

Chapter 7: Roof Assembly

Attaching the Roof Panels

Roof panels overlap the previous roof panel, giving protection from outside elements.

Before You Begin

Ensure all A-frame roof rafter assemblies are installed, and ensure all intermediate purlins are installed
and properly tightened. Predetermine the manway access location.

What You Should Know

For adjustment purposes, roof panels will be installed to each rafter first, causing exposed gaps between
each roof panel group (see figure below). After all roof panels are installed, ensure that all installed hard-
ware (flange bolts with sealing washers and flange nuts) are tightened to secure the roof panels.

Figure 7-34 Roof panel overview

A

Lower roof panel (CTR-0113)

C

Upper roof panel (CTR-0112)

B

Exposed gap

1. With assistance, position a lower roof panel (A) onto the first rafter in any A-frame.

2. Install five flange bolts (D) and five flange nuts (E) into the lower portion of the lower roof panel secur-

ing the lower roof panel to the eave angle.

3. With assistance, position another lower roof panel (A) onto the next rafter in the A-frame.

NOTE: There should be an exposed gap between the two lower roof panels in the A-frame.

4. Install five flange bolts (D) and five flange nuts (D) into the lower portion of the lower roof panel secur-

ing the lower roof panel to the eave angle.

118

Pneg-4105A 105 Ft Diameter 40-Series Bin