3 level measurement – VEGA VEGADIF 65 Foundation Fieldbus User Manual
Page 59
59
8 Setup
VEGADIF 65 • Foundation Fieldbus
36130-EN-130417
For this purpose, open valves A, B (if available) as well as 2, 4:
Medium flows in
If necessary, clean the differential pressure lines: - with gases by
blowing out with compressed air - with liquids by rinsing.
3)
For this purpose close valve 2 and 4, i.e. block the instrument.
Then open valve 1 and 5 so that the effective pressure lines blow
out/rinse.
Close valves 1 and 5 (if available) after cleaning
3. Remove air from instrument:
Open valves 2 and 4: Medium flows in
Close valve 4: Minus side is closed
Open valve 3: Equalisation plus and minus side
Briefly open valve 6 and 7, then close again: Fill the measuring
instrument completely with the medium and remove air
4. Carry out a position correction if the following conditions apply. If
the conditions are not fulfilled, then carry out the position correc-
tion after step 6.
Conditions:
The process cannot be sealed off.
The pressure extraction points (A and B) are at the same geo-
desic height.
5. Put measurement loop into operation:
Close valve 3: Separate plus and minus side
Open valve 4: Connect minus side
Now:
Valves 1, 3, 5, 6 and 7 are closed
4)
Valves 2 and 4 are open
Valves A and B open
6. Carry out position correction, if flow can be blocked. In this case,
step 5 is not required.
Then carry out adjustment, see chapter "Set parameters".
8.3 Level measurement
For level measurements, all versions of VEGADIF 65 are employed.
VEGADIF 65 with double chemical seal is immediately ready for
operation.
The VEGADIF 65 without chemical seal or with single chemical seal
is ready for operation after opening a blocking valve, in case one is
present.
Before you adjust VEGADIF 65 without chemical seal or with single
chemical seal, the effective pressure lines must be cleaned and the
instrument filled with the medium.
Instructions
3)
Arrangement with 5 valves.
4)
Valves 1, 3, 5: Configuration with 5 valves.