VEGA VEGADIF 65 Foundation Fieldbus User Manual

Page 22

background image

22

4 Mounting

VEGADIF 65 • Foundation Fieldbus

36130-EN-130417

+

1

2

3

3

5

5

6

4

Fig. 18: Measurement setup, flow measurement in vapours
1 Condensate vessels

2 Orifice or impact pressure probe

3 Blocking valves

4 VEGADIF 65

5 Drain or blow-off valves

6 3-fold valve block

When using a 5-fold valve block, the drain or blow-off valves are

already integrated.
1. Mount VEGADIF 65 below the measurement loop so that the ef-

fective pressure lines are always filled with liquid and gas bubbles

can bubble up to the process line

2. For measurements in products with solid content such as e.g.

dirty liquids, the installation of separators and drain valves is

recommended to enable collection and removal of debris and

sediment.

3. Fill the effective pressure lines to the height of the condensate

vessels before setup

In liquids